Showcasing our growing fleet of MAVERICK solar arrays across Australia
Port Bonython, SA
5B deployed
2.1MWp – 62 MAVs
in 2019, taking
21 days
on site with a
team of 3
Albury Landfill, NSW
5B deployed
1.5MWp – 44 MAVs
in 2019, taking
15 days
on site with a
team of 3
PWC Minor Centres, Borroloola & Timber Creek, NT
5B deployed
843kWp – 67 MAVs
in 2019, taking
14.5 days
on site with a
team of 3
Capital East Solar Development, Bungendore, NSW
5B deployed
500kWp – 40 MAVs
in 2018, taking
2.5 days
on site with a
team of 3
Solar Rentals, Swan Hill, VIC
5B installed
271kWp – 34 MAVs
in 2019, taking
3 days
on site with a
team of 3
Smithfield, Sydney NSW
5B deployed
120kWp – 9 MAVs
in 2018, taking
1 day
on site with a
team of 3
Wodonga, VIC
5B installed
98kWp – 9 MAVs
in 2018, taking
1 morning
on site with a
team of 2

Beverford VIC
5B deployed
99kWp – 9 MAVs
in 2017, taking
1 morning
on site with a
team of 2
Scone, NSW
5B deployed
98kWp – 9 MAVs
in 2017, taking
2 days
on site with a
team of 3
Pokolbin, NSW
5B deployed
89kWp – 8 MAVs
on site in 2017, taking
1 day
with a
team of 3

Polldale, Dubbo, NSW
5B installed
87kWp – 8 MAVs
in 2019, taking
1 morning
on site with a
team of 2
Oil Wells, Moomba Basin SA
5B deployed
60kW – 6 MAVs
in 2018, taking
1 morning
on site with a
team of 2

Euroa, VIC
5B deployed
54kWp – 5 MAVs
in 2018, taking
1 morning
on site with a
team of 2
Beverley WA
5B deployed
44kWp – 4 MAVs
in 2017, taking
1 morning
on site with a
team of 2
Robertson, NSW
5B deployed
36kWp – 3 MAVs
in 2017, taking
1 morning
on site with a
team of 2
Gidgegannup, WA
5B deployed
36kWp – 3 MAVs
in 2017, taking
1 morning
on site with a
team of 2
Mittagong, NSW
5B deployed
26kWp – 2 MAVs
in 2016, taking
As little as 15 minutes
on site with a
team of 2

Gannawarra, VIC
5B deployed
22kWp – 2 MAVs
in 2017, taking
1 morning
on site with a